Andamento da Obra
Percentuais executados até
MARÇO/26
LOCAÇÃO DA OBRA
100%
DEMOLIÇÃO
100%
MOVIMENTO DE TERRA
100%
CONTENÇÕES
100%
FUNDAÇÃO
100%
ESTRUTURA
100%
ALVENARIA
91.13%
MASSA INTERNA
75.96%
DRYWALL
87.83%
PORCELANATO INTERNO
53.83%
INST. ELÉTRICAS
33.83%
INST. HIDROSSANIT.
63.63%
AVANÇO FÍSICO
55.06%