Andamento da Obra
Percentuais executados até
JANEIRO/26
ESTRUTURA
100%
ALVENARIA
78.67%
MASSA INTERNA
57.31%
DRYWALL
73.1%
PORCELANATO INTERNO
21.12%
INST. ELÉTRICAS
16.2%
INT. HIDROSSANIT.
36.52%
AVANÇO FÍSICO
46.56%